Measure the length and width of the slab in feet, and the thickness in inches. Enter the waste factor and concrete price per cubic yard to estimate the total concrete needed and material cost.

ft

Length of the slab in feet.

ft

Width of the slab in feet.

in

Thickness of the slab in inches.

%

Extra concrete for spillage and over-excavation.

$/yd³

Average ready-mix concrete cost per cubic yard.

Slab area
– ft²
Volume (cubic feet)
– ft³
Volume (cubic yards)
– yd³
Concrete needed
– yd³
Concrete material cost
– $

    How It Is Calculated

    This calculator estimates the amount of concrete needed for a rectangular slab and its material cost. The calculations follow these steps:

    1. Slab area: Multiply length by width.

      Slab area (ft²) = L × W

      where L is length in feet and W is width in feet.
    2. Volume in cubic feet: Multiply slab area by thickness converted to feet.

      Volume (ft³) = Slab area × (T / 12)

      where T is thickness in inches.
    3. Volume in cubic yards: Divide cubic feet by 27.

      Volume (yd³) = Volume (ft³) / 27

    4. Concrete needed with waste: Add the waste percentage.

      Concrete needed (yd³) = Volume (yd³) × (1 + W / 100)

      where W is the waste factor in percent.
    5. Material cost: Multiply concrete needed by price per cubic yard.

      Cost ($) = Concrete needed (yd³) × P

      where P is the price per cubic yard in dollars.

    Assumptions

    Worked Example

    For a slab with Length = 10 ft, Width = 10 ft, Thickness = 4 in, Waste factor = 10%, and Concrete price = 150 $/yd³:

    1. Slab area = 10 ft × 10 ft = 100 ft²
    2. Volume (ft³) = 100 ft² × (4 in / 12) = 33.33 ft³
    3. Volume (yd³) = 33.33 ft³ / 27 = 1.23 yd³
    4. Concrete needed = 1.23 yd³ × (1 + 10/100) = 1.35 yd³
    5. Material cost = 1.35 yd³ × 150 $/yd³ = 202.50 $

    Results: Slab area = 100 ft², Volume (cubic feet) = 33.33 ft³, Volume (cubic yards) = 1.23 yd³, Concrete needed = 1.35 yd³, Concrete material cost = 202.50 $.

    Practical Tips

    Questions and answers

    Why do I need to include a waste factor?

    The waste factor accounts for concrete lost during pouring, spillage, over-excavation, or rounding up to the nearest batch size, ensuring you have enough material.

    Can I use this calculator for circular slabs?

    No, this calculator is designed for rectangular slabs only. For circular or irregular shapes, use a specialized concrete calculator.

    Does the price include delivery or labor?

    No, the price per cubic yard is for the concrete material only. Delivery fees and labor costs are separate and should be added manually.

    What if my slab thickness is in inches but I need it in feet?

    The calculator automatically converts thickness from inches to feet by dividing by 12, so you can enter thickness in inches directly.

    Last reviewed: 2026-10-17. Results are estimates for planning. Check them before you rely on them for design, purchase or safety decisions.