Calcmeister

Concrete foundation calculator

Measure the length and width of the foundation in feet, and the thickness in inches. Enter the concrete price per cubic yard to estimate material cost.

ft

Length of the foundation slab.

ft

Width of the foundation slab.

in

Thickness of the concrete slab.

%

Extra concrete for spillage and over-excavation.

$/yd³

Cost per cubic yard of delivered concrete.

Concrete volume
– yd³
Concrete volume
– ft³
Concrete weight
– lb
Concrete material cost
– $

    How It Is Calculated

    This calculator estimates the volume, weight, and material cost of concrete needed for a rectangular foundation slab. The calculations follow these steps:

    1. Compute the slab volume in cubic feet: Vft³ = L × W × T / 12, where L is length (ft), W is width (ft), and T is thickness (in).
    2. Convert to cubic yards: Vyd³ = Vft³ / 27.
    3. Apply the waste factor: Vtotal = Vyd³ × (1 + w / 100), where w is the waste percentage.
    4. The final volume in cubic yards is Vtotal rounded to 2 decimals.
    5. Volume in cubic feet: Vft³,total = Vtotal × 27, rounded to 1 decimal.
    6. Weight: Wlb = Vtotal × 4050, rounded to the nearest pound.
    7. Material cost: C = Vtotal × P, where P is the price per cubic yard, rounded to 2 decimals.

    Vft³ = L × W × T / 12

    Vyd³ = Vft³ / 27

    Vtotal = Vyd³ × (1 + w / 100)

    Wlb = Vtotal × 4050

    C = Vtotal × P

    Assumptions

    Worked Example

    For a slab with Length = 20 ft, Width = 20 ft, Thickness = 4 in, Waste factor = 10%, and Concrete price = $150/yd³:

    1. Vft³ = 20 × 20 × 4 / 12 = 133.33 ft³
    2. Vyd³ = 133.33 / 27 = 4.938 yd³
    3. Vtotal = 4.938 × (1 + 10/100) = 5.432 yd³ → 5.43 yd³
    4. Vft³,total = 5.432 × 27 = 146.6 ft³ → 146.6 ft³
    5. Wlb = 5.432 × 4050 = 21992 lb → 21992 lb
    6. C = 5.432 × 150 = 814.8 → $814.50 (rounded to 2 decimals)

    These results match the example outputs.

    Practical Tips

    Related calculators

    Calculators that go with this one:

    Questions and answers

    What is a waste factor and why should I include it?

    A waste factor accounts for concrete lost during pouring, spillage, or over-excavation. Including it ensures you order enough concrete to complete the job without running short.

    Can I use this calculator for circular or irregular foundations?

    No, this calculator assumes a rectangular slab with uniform thickness. For other shapes, you need to calculate the volume manually or use a different tool.

    Why is the concrete weight important?

    Knowing the weight helps you plan for transportation, formwork strength, and structural load. It is also useful for estimating disposal or reinforcement needs.

    Does the concrete price include delivery and labor?

    No, the price per cubic yard is for the material only. Delivery fees, taxes, and labor costs are separate and vary by supplier and location.

    Last reviewed: 2026-10-17. Results are estimates for planning. Check them before you rely on them for design, purchase or safety decisions.